Structural steel nearing completion. Metal pan deck on mezzanine in preparation for concrete pour. Roof deck completed and metal frames installed for skylights.
Selective demolition underway on existing building façade. Crew is removing former mansard roof which will be replaced with a more contemporary stucco façade.
View from the rear of the building. Sloped roof steel to promote drainage, backfill of foundation and storm water inlet piping is underway.
View inside the warehouse. New stair tower and stairs to storage mezzanine are complete. Rough grading is underway in preparation for layout and installation of underground utilities.
View of front of building. Crews are staging masonry materials in readiness for constructing exterior walls while steel erectors install safety cabling on the mezzanine.
Comments are closed.